Technical Services Division is one of the prime departments of the MMG that has been providing technical construction services to the industry since the 1950’s. However the division was formally set up as a separate entity in late 90s to meet the requirements of the local industrial manufacturers and started serving direct clients in the field of specialized services. In 2005 Technical Service Division entered into the field of maintenance and since then has successfully completed several maintenance and T/A jobs for Saudi Aramco, SABIC, Saudi Chevron and others. In the past three years the Technical Services Division has successfully completed projects worth SR75 million.
Services
The division provides services in the area of Engineering, Plant Shut down and Maintenance, Scafolding, Specialized Services, Plant Modification and Revamping and Electrical, Instrumentation and Control System.
In Engineering, the Technical Services Division collaborates with Jedson of the United States. In specialized Services, the division collaborates with Dutch company, Lion and render services in the area of chemical cleaning, oil flushing, cold cutting, bolt torque and tensioning, pressure testing and pipeline scrapping.
Under Maintenance the division undertakes complete project management, static equipment maintenance, rotary equipment management, structural piping and all fabrication work and hydro-jetting services.
In Electrical, Instrumentation and Control System, Technical Services Division in collaboration with Pakistan’s UEC specializes in revamping of the projects, control system installation, local instruments and panel, instrument cabling and wiring fire and gas detection system, grounding and lightning system, optimized material selection and testing and Commissioning.
To achieve the corporate vision, the Technical Services Division has set its own vision and mission:
Vision
To be the Client preference in performing all Industrial Technical Support and Maintenance Activities by providing Integrated Solutions and Services.
Mission
To deliver an ultimate quality service with extensive consideration on HSE (Health, Safety & Environment) requirements.
Quality
MMG is a ISO 9001: 2008 certified group. In addition it possesses several ASME certifications that include ASME “P” for fabrication and assembly of pressure piping; ASME “U” for manufacture of pressure vessels; ASME “S” for manufacture and assembly of power boilers; ASME “A” for assembly of power boilers; and ASME “R” for Repair and Alterations of pressure vessels and boilers.
Completed and on-going projects
Shut-down and Maintenance
S.No |
Client / Project |
Work Description |
Period |
Location |
01 |
Saudi Aramco Qatif GOSP, PO: 6510431698 |
Repair chiller – Nozzle Replacement – Q05-D-392 |
On-Going June 2010 |
Qatif |
02 |
Saudi Aramco Ras Tanura Refinery,
PO: 6510428878 |
General Services - Plant J06 & J72 |
To Start July 2010 |
Rastanura |
03 |
Saudi Aramco, Ras Tanura Refinery.
PO : 6510398537 |
Manpower Support , Heater Tubes Replacement |
Nov ‘09 to Jan‘10 |
Rastanura |
04 |
Saudi Aramco, Riyadh Refinery. PO : 6600020778 |
50” Falre Header Replacement (T&I 2009) |
Dec ‘08 to Jun ‘09 |
Riyadh |
05 |
Saudi Arabian Fertilizer Co. (SAFCO) / UHDE Arabia Ltd. PO : 5475 |
CO2 Condensate Pump - Piping installation & Tie-in works |
Sep ‘08 to Oct ’08 |
Jubail |
06 |
Saudi Aramco – Hawiyah & Haradh Gas Plant . PO : 6510279427 |
Revalidation of Gas Well Flow Lines (31 Headers) |
Nov ‘07 to Feb ’08 |
Hawiyah & Haradh |
07 |
Saudi Arabian Fertilizers Co. (SAFCO) / UHDE Arabia Ltd. PO : 95-3036-IK-005 |
SAFCO IV T&I – Deficiency Rectification work |
Jan ‘08 to Feb ’08 |
Jubail |
08 |
Saudi Aramco, Riyadh Refinery. PO : 6510227988 |
Tubes Replacement of Platformate Heater 301 H1/H2/H3 (T&I 2007) |
Jan ‘07 to Feb ‘07 |
Riyadh |
09 |
Saudi Aramco, Riyahd Refinery / Technip
PO : SPO – 297 |
Pump Vibration - Suction Piping Welding and Alignment Correction |
Feb ’07 |
Riyadh |
10 |
Saudi Chevron Phillips (SCP) PO : ACP-1957-EXP |
Modification of Column internal and Tray repair
C1600, C1610, C1700 & C 1720 |
Nov ‘06 to Mar 07 |
Jubail |
11 |
Saudi Aramco – Shedgum Gas Plant / A.R. Al-Bader Est.
PO : 11971 |
Post Weld Heat Treatment – Pipe Welds |
July ’07 |
Shedgum / Abqaiq |
12 |
Saudi Aramco – Shedgum GOSP 5. PO : 6510207236 |
48” Flare Stack Repair
(Cold Cutting & Welding) |
Sep ’06 |
Shedgum / Abqaiq |
Chemical Cleaning
Sl. No. |
Client / Project |
Work Description |
Period |
Location |
1 |
Saudi Aramco – Safania Off-Shore |
Chemical Cleaning of Gas Cooler – E101 |
June 2010 |
MMG TSD Workshop - Dammam |
2 |
Saudi Aramco – Abqaiq Gas Plant |
Chemical Cleaning of Glycol De-Hydration Unit |
April 10 to May 2010 |
Abqaia |
3 |
Eastern Petrochemicals Company (SHARQ) / Foster Wheeler [PO# 6CF02-SC15/00] |
Off Plot Pipeline Scraping & Chemical cleaning |
Sep 08 to Apr 09 |
Jubail |
4 |
Saudi Aramco – Juaymah Gas Plant Expansion Project / Tecnicas Reuindas (TRG) [PO # 6CT01-SC14/00] |
Chemical Cleaning of ADIP, Refrigeration, Lube Oil and BFW systems & N2 Padding |
Sep 08 to March 09 |
Juaymah |
5 |
Petro Rabigh / Mitsui Engineering & Ship Building Company Ltd [MESAR] [PO # MMG08-RAB-DC63/00] |
Chemical Cleaning of O2, CO2 and EO Reactor Systems & N2 Padding |
May 08 to Dec 08 |
Rabigh |
6 |
Eastern Petrochemicals Company (SHARQ) / Samsung Engineering & Const. Co., [PO # PO-S-PC-002] |
Passivation of Cooling Water System |
Jan 08 to March 09 |
Jubail |
7 |
Jubail Chevron Philips (JCP) [PO #JCP-0241] |
Boil out / Degreasing of Boilers V-7650, V-7645 & V-7640 |
2007/2008 |
Jubail |
8 |
Saudi Aramco, Safaniya [PO # 6510278840] |
Chemical Cleaning of Heat Exchanger E-201 A/B |
November 07 |
MMG TSD Workshop- Dammam |
9 |
Saudi Chevron Philips (SCP) [PO #4502792584] |
Decontamination of Columns, Vessels & Drums [C-1720, C-1700 E-1720A/B/C, & D-1720] |
October 07 |
Jubail |
10 |
Saudi Chevron Philips (SCP) [PO #SCP-1957-EXP] |
Decontamination of Columns, Vessels & Drums [C-1720, D-1720 E-1720A/B, C-1710, E-1700, C-1600, E-1610, E-1606, D-1610 & C-1220] |
January 07 |
Jubail |
11 |
Jubail United Petrochemical Company / Linde Arabian Co. Ltd., (LAO) [PO # R6P001-001] |
Passivation of Cooling Water Pipelines |
July 06 |
Jubail |
12 |
Saudi Aramco, Safaniya [PO # 6510183263] |
Chemical Cleaning of Gas Cooler (Tube side) 4-E-301 |
April 06 |
MMG TSD Worshop - Dammam |
13 |
Jubail United Petrochemical Co., (JUPC) / Toyo Engineering Saudi Arabia Ltd., (SATEC) EO/EG Project [PO # 4CT01-SC-26/00] |
Chemical Cleaning of O2 & N2 Pipelines and Nitrogen Padding |
February 06 |
Jubail |
Pipeline Scrapping
Sl. No. |
Client / Project |
Work Description |
Period |
Location |
1 |
Eastern Petrochemicals Company (SHARQ) / Foster Wheeler - U&O |
U&O Pipeline Flushing & Air blow work |
July 09 to Sep 09 |
Jubail |
2 |
Eastern Petrochemicals Company (SHARQ) / Foster Wheeler – OFF PLOT [PO# 6CF02-SC15/00] |
Off Plot Pipeline Scraping & Chemical cleaning |
Sep 08 to Apr 09 |
Jubail |
3 |
Saudi Aramco – Hawiyah & Haradh Gas Plant [PO # 6510279427] |
Revalidation of Gas Well Flow Lines |
Nov 07 to Feb 08 |
Hawiyah & Haradh |
4 |
Jubail Chevron Philips (JCP) [PO # JCP-0124] |
Dewatering, Scraper Cleaning, Drying and Preservation (16 KM Long pipelines) |
Aug 06 |
Jubail |
Oil Flushing
Sl. No. |
Client / Project |
Work Description |
Period |
Location |
1 |
Saudi Aramco – Abqaiq Gas Plant / Fouad Abdulla Fouad Co. Ltd., [PO # 13044 CM] |
Lube Oil Flushing of Compressor Lube oil lines |
Jun 07 to Aug 07 |
Abqaiq |
2 |
Saudi Aramco, GOSP - Qatif / Arabian CBI [PO # 128150 & POF-8101 & 4FC01-PR-02] |
Chemical Cleaning and Oil Flushing of Pump LO piping |
June 04 to Jan 05 |
Qatif |
Hydraulic Bolt Torque & Tensioning
Sl. No. |
Client / Project |
Work Description |
Period |
Location |
1 |
Saudi Aramco – Hawiyah NGL . PO:6510423640, 6510423456, 6510422487 |
Bolting Services (Torque) |
Arp 10 – Aug 10
(on-Going) |
Hawiyah |
2 |
Saudi Aramco – UGP. PO: 6510418609 |
Bolting Services (Torque) |
May 10 |
Uthmaniyah |
3 |
SASREF- Balance of Plant / CB&I Lummus [po # 7CL02-SC40/00] |
Bolting Services (Torque and Tensioning) |
From Aug 09 |
Jubail |
4 |
SABIC- Saudi Kayan – Package K-022 & K-024 / Flour Arabia [PO # 7CS04-SC28/00] |
Bolting Services (Torquing and Tensioning) |
From March 09 |
Jubail |
5 |
Saudi Aramco – Khurais KCC Project (GOSP-3 & 4) / SAIPEM PO # 8CS02/SC15/00] |
Bolting Services (Torquing and Tensioning) |
March 09 to July 09 |
Khurais |
6 |
Jesco Seamless Pipe Plant Project / Danieli [PO # 8CJ03-SC08/00] |
Bolt Torquing and Tensioning |
Dec 08 to August 09 |
Jubail |
7 |
SABIC - Yanbu National Petrochemicals Company (Yansab - EG-1 Project) / Saudi Toyo Engineering Co., [PO # P-135 & 278] |
Bolt Torquing and Tensioning |
Sep. 08 to Jan. 09 |
Yanbu |
8 |
Saudi Aramco – Juaymah Gas Plant Project / Technicas Reundas [PO # 6CT01-SC18/00] |
Bolt Torquing & Tensioning |
Sept. 07 to July 09 |
Juaymah |
9 |
Saudi Aramco – Water Injection Pump Station (WIPS) Facilities Project / SAIPEM [PO # 7CS02/SC18/00] |
Bolt Torquing & Tensioning |
Sept. 07 to July 09 |
Ain Dar, Uthmaniyah, Hawiyah & Haradh |
10 |
Saudi Chevron Philips / Jubail Chevron Philips Project / Parson [PO # 834/010193-010130] |
Bolt Tensioning |
Oct. 07 |
Jubail |
11 |
SABIC - Yanbu National Petrochemicals Company (Yansab - EG-1 Project) / Saudi Toyo Engineering Co., |
Anchor Bolt Tensioning |
Oct. 07 |
Yanbu |
12 |
TASNEE Project |
Bolting Services |
Aug.07 |
Jubail |
13 |
Jubail United Olefins Complex, JUEG-EO/EG Project, / Saudi TOYO Engineering Co., |
Bolting Services |
May 06 to June 2007 |
Jubail |
Cold Cutting
Sl. No. |
Client / Project |
Work Description |
Period |
Location |
1 |
Saudi Aramco , Uthmaniyah GOSP 4
PO# 6510431356 |
Modification of 12” & 16” welded body valves – Cold Cutting and Welding |
June 10 |
Uthmaniyah |
2 |
Saudi Aramco, Riyadh Refinery [PO # 6600020778] |
50” Flare Line Replacement |
Dec 08 to June 09 |
Riyadh |
3 |
Saudi Aramco – Shedgum GOSP-5 [PO # 6510207236] |
Repair of 48” Flare Stack (Cold cutting and Welding) |
Sep 06 |
Shedgum / Abqaiq |
4 |
Saudi Aramco – Berry Gas Plant / Technip [PO # 2124/POF/806-R18] |
Cold Cutting work at Unit at A475 SRU 100 (Qatif Facilities) |
July 05 |
Jubail |
5 |
Saudi Aramco – Berry Gas Plant / Technip [PO # 2124/POF/806-R17] |
Cold Cutting work at Unit at A475 SRU 200 (Qatif Facilities) |
March 05 |
Jubail |
Pressure Testing
Sl. No. |
Client / Project |
Work Description |
Period |
Location |
1 |
Saudi Aramco – Hawiyah & Haradh Gas Plant [PO # 6510279427] |
Revalidation of Gas Well Flow Lines |
Nov 07 to Feb 08 |
Hawiyah & Haradh |
|
|